Modern Slaughterhouses Yet To Be Operational In City


golmaal govindam

Recommended Posts

[font=Georgia,]

While imported machinery is ready in some cases, delay in civil works has slowed down the progress[/font][color=#3B3A39][font=Georgia,]
Illegal manual slaughtering of animals in different parts of the city is likely to continue for some more time. Clearly, it will take another four months or more before the four modern slaughter houses become operational.[/font][/color][color=#3B3A39][font=Georgia,]
Construction of modern slaughterhouses has been underway at Amberpet, New Bhoiguda, Gowlipura and Ramnaspura for the last couple of years and they were supposed to be operational in December, 2010. The units are coming up at the very place where manual slaughtering was happening.[/font][/color][color=#3B3A39][font=Georgia,]
The municipal corporation banned the practice once the first modern abattoir at Chengicherla was opened eight years ago. Yet, it could never prevent the manual slaughtering at the sites forcing the government to take up constructing of the modern abattoirs. Along with these is the dry rendering plant near the Chengicherla abattoir.[/font][/color]
[color=#3B3A39][font=Georgia,]
[url="http://www.thehindu.com/news/cities/Hyderabad/article3449788.ece"]http://www.thehindu.com/news/cities/Hyderabad/article3449788.ece[/url][/font][/color]