Pattiseema Project


aadwi

Recommended Posts

started on march 29th

 

http://youtu.be/X3JITM2kEcU

 

20th may ki 20% works compltd

 

 

http://youtu.be/gR5_qpkoJRk

 

 

12km distance owrk compltd til now , 4 km reaaning

 

http://youtu.be/pHAClhIlucs

Link to comment
Share on other sites

  • Replies 34
  • Created
  • Last Reply

Top Posters In This Topic

  • aadwi

    9

  • posaanisam

    8

  • micxas

    5

  • BoltOptions

    2

august 15 ki 1st phase finish cheyali ani dead line

 

12km woks compltd

 

4 km reaming

 

total 8 pipe lines , 200 engineers , 1200 daily workers , cc cams all around to inspect frm office itself

 

 

polavrm right canal 180 km , dis canal divided into 7 sections , 4 sections completd ,  2 5 6  sections remaining